When IKEA received new guard booths

The Assignment

Due to new customs regulations, IKEA needed to quickly establish two new gatehouses and security booths at its distribution center in Älmhult. The requirements were clear: high security classification, extensive technical equipment, and short delivery time.

The Solution

In autumn 2020, MG Link delivered two modular buildings – from foundation works to occupancy in approximately two months. Both buildings were specially adapted in Swedish modular production to accommodate all technical equipment required for remote control of gates and surveillance cameras across the large site.

  • Security-rated windows, non-opening and fitted with privacy protection
  • Motorized service hatches for handling drivers, freight documents, and customs documentation
  • Internal access control systems dividing the buildings into separate security zones

North Gatehouse (larger building)

Constructed from six 9-meter modules with a pitched roof and designed for efficient operations with clear zone division. The facility includes:

  • Reception area for transport operators
  • IKEA personnel handling documentation for entry and exit within the bonded zone
  • Securitas staff monitoring gates, cameras, and scanning equipment
  • Shared facilities including kitchen, locker room, cleaning room, and restrooms
  • Driver accommodation room for overnight drivers (locker room, shower, wash facilities, and fresh water)
  • A total of five departments and technical rooms, all separated by access control systems

South Guardhouse (smaller building)

Consists of two modules but houses equally advanced technical equipment as the larger building. Here, Securitas manages surveillance of entry and exit points in the southern part of the site.

Result

  • Rapid delivery from groundwork to operation in approximately 2 months
  • High security level with zone division and certified components
  • Technically optimized operations for remote control and document handling
  • User-friendly logistics for drivers and staff

Key Facts

  • Client: IKEA, Distribution Center Älmhult
    Supplier: MG Link
  • Delivery: Autumn 2020 (~2 months)
  • Number of buildings: 2 (North Gatehouse & South Guardhouse)
  • Modules: North: 6 × 9 m • South: 2 modules
  • Roof: Pitched roof on both buildings
  • Security/Technology: Security-rated windows with privacy protection, motorized service hatches, internal access control systems, remote control of gates and cameras
  • Functions: Reception, security control center (Securitas), IKEA document handling, driver room, shared facilities